Project we are proud of
Slope Erosion Control System at His Majesty Sultan Haitham Bin Tariq Villa, Boushar
Road & Highway

Project details
Location: Boushar, Oman
Client: Roadline
Scope: Design, Supply and Application of Slope Erosion Control System
Engineered Erosion Control for a High-Profile Landscape
For this landmark villa in Boushar, TEICO, through Marmol Integrated, delivered a specialized erosion control system for a critical slope section within the property.
The requirement called for a durable, precise, and visually integrated solution—capable of protecting the landscape while preserving the area’s natural aesthetic.
With 1,500 m² of treated slope area, the project demonstrates how technical engineering and architectural sensitivity can be combined to deliver a long-lasting, environmentally aligned outcome.
A key slope within the villa grounds required intervention to prevent surface erosion and long-term degradation.
The site demanded an engineered solution that balanced structural performance, sustainability, and visual harmony with the surrounding landscape.
Project Details
Project: His Majesty Sultan Haitham Bin Tariq Villa at Boushar
Scope of Work: Design, Supply, and Application of Erosion Control System
Quantity: 1,500 m²
Challenges
Susceptibility to Surface ErosionThe exposed slope faced risks from runoff, rainfall concentration, and progressive surface wear.
Aesthetic RequirementsThe solution needed to blend seamlessly with the villa's landscape while maintaining integrity and performance.
Environmental PerformanceMaterials and methods had to reflect sustainability objectives and minimize resource consumption.
Solutions
1. Geotechnical Assessment
Conducted site investigation to evaluate slope geometry, surface conditions, and erosion patterns.
Identified areas requiring surface reinforcement and drainage improvement.
2. Custom Erosion Control Design
Developed a tailored system integrating geosynthetics and surface reinforcement.
Selected materials compatible with both performance criteria and aesthetic requirements.
3. Precision Installation
Applied engineered materials across the 1,500 m² slope area.
Used reinforcement and surface protection layers to increase resistance against erosion.
4. Integrated Drainage
Added drainage features to manage runoff flow paths.
Reduced risk of water-induced erosion and ensured long-term stability.